Increasing Prices Globally

This is a very useful function for adjusting the price of inventory parts. Before using this tool, it is extremely important to understand what it does and how it works. Otherwise, there could be some big surprises after the tool has been run.

Smart pricing gives the user the ability to set pricing using cost ranges by supplier, parts department or type of work. You will now be able to price inventory parts using smart pricing matrices.

To Run a Global Price Increase

You can increase the price based on the:

NOTE: All users must exit every module of R.O. Writer in every workstation in your shop.

Complete these steps:

  1. Click the Global Pricing button in the toolbar. As a safeguard, you are prompted to continue.
  2. All users must exit R.O. Writer completely (the main and any other module that's open) before proceeding so R.O. Writer can back up the database.

  3. Click Yes to back up the database. The backup database is named "InvBack.mdb" and placed in the in the ROWriter\Backup directory.

  4. Click OK to update prices.

  5. Click OK to complete the process.

Increase Based On Average Cost

This option will adjust the prices charged at the five different levels of defined customers based on the average cost of each part that the shop has purchased.

If the average cost for a part is $0.00, then the new price will be $0.00. If the multiplier at any level is 0.00, the new price at that level will be $0.00.

When updating part prices using Global Pricing based on average cost,

Parts Conditions

Select which parts department to include in the price adjustment. You can select individual or all departments.

Next, select the cost range.

The cost range is the range of average costs to be used in the pricing adjustments. For instance, if the idea were to increase prices on all parts with an average cost between $3.00 and $5.00, these values would be entered in the cost range.

By entering a range, the Adjust for All Costs box is unchecked. Selecting the Adjust for All Costs box will reset the cost range figures to 0.00, and all parts, regardless of their average cost, will be adjusted.

Adjustments

Since this is an adjustment based on average cost, the Cost option is selected. Next, the Multiplier, % Profit, or % Markup must be entered for each price level. A change to any one of these fields within a pricing level will automatically adjust the other two. If a level is left at 0.00, the part is priced at $0.00. If the average cost for a part is $0.00, the price charged for all pricing levels will be $0.00.

If the average cost of a part is $5.00, and multipliers of 1.70, 1.60, 1.50, 1.40, and 1.30 were entered for the respective pricing levels, the new prices would be $8.50, $8.00, $7.50, $7.00, and $6.50. Select OK to update the prices, or Cancel to stop the change.

NOTE: If a single parts department is selected, and the multipliers are adjusted to increase prices, the existing multipliers for that department are not adjusted. To change the default multipliers for the department, see Parts Departments if the CPM method was set up for Inventory Pricing or Default Inventory Pricing if one of the other methods is selected.

Increase Based on Current Price

This option will adjust the prices charged to the five different levels of defined customers based on the existing price set at each pricing level. The pricing for a part may be adjusted each time a part is posted to inventory using Post Parts Receipts, PO Management, or AP Detail Post.

When updating part prices using Global Pricing based on Current Pricing,

The existing price at each level is multiplied by the % markup for each price level to determine the new price. If the current price for a part at a level is $0.00, then the new price at that level will be $0.00. If the % markup at any level is 0.00, the new price at that level will be the same as the old price.

Parts Conditions

Select which parts department to include in the price adjustment. You can select individual or all departments.

Next, select the cost range.

The cost range is the range of average costs to be used in the pricing adjustments. For instance, if the idea were to increase prices on all parts with an average cost between $3.00 and $5.00, these values would be entered in the cost range.

By entering a range, the Adjust for All Costs box is unchecked. Selecting the Adjust for All Costs box will reset the cost range figures to 0.00, and all parts, regardless of their average cost, will be adjusted.

Adjustments

Since this is an adjustment based on current price, the Current Pricing option is selected. Next, the % Markup must be entered for each price level. Notice that the cost may also be adjusted. If the current price for a part at a level is $0.00, then the new price will be $0.00. If the % markup at any level is 0.00, the new price at that level will be the same as the old price.

If the current prices are $8.50, $8.00, $7.50, $7.00, and $6.50, and a % Markup of 0.10 (10% increase) is entered for the respective pricing levels, the new prices would be $9.35, $8.80, $8.25, $7.70, and $7.15. Select OK to update the prices, or Cancel to stop the change.